DERRICK
ADKINS CONSTRUCTION COMPANY
Partial
Income Statement
Year
Ended December 31, 2004
_____________________________________________________________
Revenue from
long-term contracts (Project 3) $500,000
Costs of
construction (Project 3) 330,000
Gross profit 170,000
Provision for loss
(Project 1)* (30,000)
*Contract
costs through 12/31/04 $450,000
Estimated costs to complete 140,000
Total estimated costs 590,000
Total contract price 560,000
Loss recognized in 2004 $ (30,000 )
DERRICK ADKINS
CONSTRUCTION COMPANY
Partial Balance Sheet
December 31, 2004
Current
assets:
Accounts receivable $90,000
($1,080,000 – $990,000)
Inventories
Construction in process $420,000 *
Less: Billings 360,000
Unbilled contract costs (Project
1) 60,000
Current
liabilities:
Billings ($220,000) in excess of
contract
costs ($126,000) (Project 2) 94,000
*The loss
of $30,000 was subtracted from the construction in process account.