(a) (1) Gross
profit recognized in 2004:
Contract price $1,000,000
Costs:
Costs to date $280,000
Estimated additional
costs 520,000 800,000
Total estimated profit 200,000
Percentage completion to date
($280,000/$800,000) 35%
Gross profit recognized in 2004 $ 70,000
Gross profit recognized in 2005:
Contract price $1,000,000
Costs:
Costs to date $600,000
Estimated additional
costs 200,000 800,000
Total estimated profit 200,000
Percentage completion to date
($600,000/$800,000) 75%
Total gross profit recognized 150,000
Less: Gross profit recognized in 2004 70,000
Gross profit recognized in 2005 $ 80,000