|
|
PROBLEM 18-5
|
|
(a) The completed-contract method of revenue recognition recognizes income
only upon completion of a project or shipment of a product. All associated
costs are expensed at the point of sale, and there are no interim charges or
credits to income. Completed-contract revenue recognition is used for
long-term projects when estimates of revenue and costs are not reliable.
The percentage-of-completion method of revenue recognition
recognizes income and associated costs in each accounting period based upon
progress. This method is preferred for long-term projects when estimates of
revenues and costs are reasonably dependable. Under the
percentage-of-completion method, the current status of uncompleted contracts is
reflected on the financial statements.
(b) Using
the data provided for the Dagmar Haze Tractor Plant, and on the assumption that
the percentage-of-completion method of revenue recognition is used, the
calculations of GMCB’s revenue and gross profit for 2003, 2004, and 2005, under
three sets of circumstances are presented below.
1. Assuming
that all costs are incurred, all billings to customers are made, and all
collections from customers are received within 30 days of billing, the GMCB’s
revenue, cost of sales, and gross profit for 2003, 2004, and 2005, are
calculated as follows:
Percentage-of-Completion (Cost-to-Cost Basis)
($000 omitted)
|
Year
|
Contract Price
|
Costs to Date
|
Estimated Total Costs
|
Estimated Gross Profit (Col. 2–Col. 4)
|
Percent
Complete (Col. 3/Col. 4)
|
|
(1)
|
(2)
|
(3)
|
(4)
|
(5)
|
(6)
|
|
2003
|
$8,000
|
$2,010
|
$6,700
|
$1,300
|
30%
|
|
2004
|
8,000
|
5,025
|
6,700
|
1,300
|
75%
|
|
2005
|
8,000
|
6,700
|
6,700
|
1,300
|
100%
|
Revenue recognition
|
Year
|
Contract Price
|
Percent Complete
|
Revenue
Recognizable
|
Less Prior Year(s)
|
Current Year
|
|
2003
|
$8,000
|
30%
|
$2,400
|
—
|
$2,400
|
|
2004
|
8,000
|
75%
|
6,000
|
$2,400
|
3,600
|
|
2005
|
8,000
|
100%
|
8,000
|
6,000
|
2,000
|
Profit
recognition
|
Year
|
Estimated Profit
|
Percent Complete
|
Revenue Recognizable
|
Less Prior Year(s)
|
Current Year
|
|
2003
|
$1,300
|
30%
|
$ 390
|
—
|
$390
|
|
2004
|
1,300
|
75%
|
975
|
$390
|
585
|
|
2005
|
1,300
|
100%
|
1,300
|
975
|
325
|
2. Assuming the same facts as in Instruction
(b)1., but that cost overruns of $800,000 were experienced, GMCB’s revenue, costs
of sales, and gross profit for 2003, 2004, and 2005 were calculated as follows:
Percentage-of-Completion
(Cost-to-Cost Basis)
($000
omitted)
|
Year
|
Contract Price
|
Costs to Date
|
Estimated Total Costs
|
Estimated Gross Profit (Col. 2–Col. 4)
|
Percent Complete (Col. 3/Col. 4)
|
|
(1)
|
(2)
|
(3)
|
(4)
|
(5)
|
(6)
|
|
2003
|
$8,000
|
$2,810
|
$7,500
|
$500
|
37.47%
|
|
2004
|
8,000
|
5,825
|
7,500
|
500
|
77.67%
|
|
2005
|
8,000
|
7,500
|
7,500
|
500
|
100%
|
Revenue recognition
|
Year
|
Contract Price
|
Percent Complete
|
Revenue Recognizable
|
Less Prior Year(s)
|
Current Year
|
|
2003
|
$8,000
|
37.47%
|
$2,997.6
|
—
|
$2,997.6
|
|
2004
|
8,000
|
77.67%
|
6,213.6
|
$2,997.6
|
3,216
|
|
2005
|
8,000
|
100%
|
8,000
|
6,213.6
|
1,786.4
|
PROBLEM 18-5 (Continued)
Profit recognition
|
Year
|
Estimated Profit
|
Percent Complete
|
Profit
Recognizable
|
Less Prior Year(s)
|
Current Year
|
|
2003
|
$500
|
37.47%
|
$187.4
|
—
|
$187.4
|
|
2004
|
500
|
77.67%
|
388.4
|
$187.4
|
201
|
|
2005
|
500
|
100%
|
500
|
388.4
|
111.6
|
3. Assuming the same facts as
in Instructions (b)1. and (b)2., but that additional cost overruns of $540,000
are experienced, GMCB’s revenue, cost of sales, and gross profit for 2003,
2004, and 2005 are calculated as follows:
Percentage-of-Completion
(Cost-to-Cost Basis)
($000 omitted)
|
Year
|
Contract Price
|
Costs to Date
|
Estimated Total Costs
|
Estimated Gross Profit (Col. 2–Col. 4)
|
Percent Complete (Col. 3/Col. 4)
|
|
(1)
|
(2)
|
(3)
|
(4)
|
(5)
|
(6)
|
|
2003
|
$8,000
|
$2,810
|
$7,500
|
$500
|
37.47%
|
|
2004
|
8,000
|
6,365
|
8,040
|
(40)
|
79.17%
|
|
2005
|
8,000
|
8,040
|
8,040
|
(40)
|
100%
|
Revenue recognition
|
Year
|
Contract Price
|
Percent Complete
|
Revenue
Recognizable
|
Less Prior Year(s)
|
Current Year
|
|
2003
|
$8,000
|
37.47%
|
$2,997.6
|
—
|
$2,997.6
|
|
2004
|
8,000
|
79.17%
|
6,333.6
|
$2,997.6
|
3,336
|
|
2005
|
8,000
|
100%
|
8,000
|
6,333.6
|
1,666.4
|
Profit recognition
|
Year
|
Estimated Profit
|
Percent Complete
|
Profit
Recognizable
|
Less Prior Year(s)
|
Current Year
|
|
2003
|
$500
|
37.47%
|
$187.4
|
—
|
$187.4
|
|
2004
|
(40)
|
100%a
|
(40)
|
$187.4
|
(227.4)
|
|
2005
|
(40)
|
100%
|
(40)
|
(40)
|
—
|
aWhen there is a projected loss at any time, it
must be recognized in full in the period in which a loss on the contract
appears probable.
No comments:
Post a Comment