Thursday, February 2, 2017

PROBLEM 18-5



PROBLEM 18-5


(a)   The completed-contract method of revenue recognition recognizes income only upon completion of a project or shipment of a product. All associated costs are expensed at the point of sale, and there are no interim charges or credits to income. Completed-contract revenue rec­ognition is used for long-term projects when estimates of revenue and costs are not reliable.

        The percentage-of-completion method of revenue recognition recog­nizes income and associated costs in each accounting period based upon progress. This method is preferred for long-term projects when estimates of revenues and costs are reasonably dependable. Under the percentage-of-completion method, the current status of uncompleted contracts is reflected on the financial statements.
(b)   Using the data provided for the Dagmar Haze Tractor Plant, and on the assumption that the percentage-of-completion method of revenue recognition is used, the calculations of GMCB’s revenue and gross profit for 2003, 2004, and 2005, under three sets of circumstances are presented below.
        1.    Assuming that all costs are incurred, all billings to customers are made, and all collections from customers are received within 30 days of billing, the GMCB’s revenue, cost of sales, and gross profit for 2003, 2004, and 2005, are calculated as follows:

Percentage-of-Completion (Cost-to-Cost Basis)
($000 omitted)



Year

Contract Price

Costs   to Date
Estimated Total Costs
Estimated Gross Profit (Col. 2–Col. 4)
Percent              Complete         (Col. 3/Col. 4)
(1)
(2)
(3)
(4)
(5)
(6)
2003
$8,000
$2,010
$6,700
$1,300
30%
2004
8,000
5,025
6,700
1,300
75%
2005
8,000
6,700
6,700
1,300
100%


        Revenue recognition

Year
Contract Price
Percent Complete
Revenue      Recognizable
Less Prior Year(s)
Current Year
2003
$8,000
30%
$2,400
$2,400
2004
8,000
75%
6,000
$2,400
3,600
2005
8,000
100%
8,000
6,000
2,000

Profit recognition

Year
Estimated Profit
Percent Complete
Revenue      Recognizable
Less Prior Year(s)
Current Year
2003
$1,300
30%
$  390
$390
2004
1,300
75%
975
$390
585
2005
1,300
100%
1,300
975
325

2.     Assuming the same facts as in Instruction (b)1., but that cost overruns of $800,000 were experienced, GMCB’s revenue, costs of sales, and gross profit for 2003, 2004, and 2005 were calculated as follows:

Percentage-of-Completion (Cost-to-Cost Basis)
($000 omitted)



Year

Contract Price

Costs   to Date
Estimated Total Costs
Estimated Gross Profit (Col. 2–Col. 4)
Percent              Complete         (Col. 3/Col. 4)
(1)
(2)
(3)
(4)
(5)
(6)
2003
$8,000
$2,810
$7,500
$500
37.47%
2004
8,000
5,825
7,500
500
77.67%
2005
8,000
7,500
7,500
500
100%

        Revenue recognition


Year
Contract Price
Percent Complete
Revenue      Recognizable
Less Prior Year(s)
Current Year
2003
$8,000
37.47%
$2,997.6
$2,997.6
2004
8,000
77.67%
6,213.6
$2,997.6
3,216
2005
8,000
100%
        8,000
6,213.6
1,786.4
PROBLEM 18-5 (Continued)

        Profit recognition

Year
Estimated Profit
Percent Complete
Profit             Recognizable
Less Prior Year(s)
Current Year
2003
$500
37.47%
$187.4
$187.4
2004
500
77.67%
388.4
$187.4
201
2005
500
100%
500
388.4
111.6

3.     Assuming the same facts as in Instructions (b)1. and (b)2., but that additional cost overruns of $540,000 are experienced, GMCB’s revenue, cost of sales, and gross profit for 2003, 2004, and 2005 are calculated as follows:

Percentage-of-Completion (Cost-to-Cost Basis)
($000 omitted)


Year

Contract Price

Costs   to Date
Estimated Total Costs
Estimated Gross Profit (Col. 2–Col. 4)
Percent              Complete         (Col. 3/Col. 4)
(1)
(2)
(3)
(4)
(5)
(6)
2003
$8,000
$2,810
$7,500
$500
37.47%
2004
8,000
6,365
8,040
(40)
79.17%
2005
8,000
8,040
8,040
(40)
100%

        Revenue recognition

Year
Contract Price
Percent Complete
Revenue      Recognizable
Less Prior Year(s)
Current Year
2003
$8,000
37.47%
$2,997.6
$2,997.6
2004
8,000
79.17%
6,333.6
$2,997.6
3,336
2005
8,000
100%
        8,000
6,333.6
1,666.4

        Profit recognition

Year
Estimated Profit
Percent Complete
Profit             Recognizable
Less Prior Year(s)
Current Year
2003
$500
37.47%
$187.4
$187.4
2004
(40)
100%a
(40)
$187.4
(227.4)
2005
(40)
100%
(40)
(40)


        aWhen there is a projected loss at any time, it must be recognized in full in the period in which a loss on the contract appears probable.

No comments:

Post a Comment

Deskripsi Tinta Printer

 Deskripsi Umum Tinta Printer Tinta printer adalah cairan berwarna (atau hitam) yang digunakan dalam printer untuk membuat gambar atau teks ...

Blog Archive